Our company Controls Vasiloglou has undertaken projects with a total capacity of 4 MWp for the 4th quarter of 2012.

Indicative projects:

  • Design and Construction of a 630 KVA (0.5 MWp) Medium Voltage Substation for a photovoltaic park in Karditsa
  • Electrical Installation of a 100 KWp Photovoltaic Park in Kozani
  • Design and Construction of a 630 KVA (0.5 MWp) Medium Voltage Substation for a photovoltaic park in Magnesia
  • Design and Construction of a 315 KVA (0.25 MWp) Medium Voltage Substation for a photovoltaic park in Kavala
  • Electrical Installation of a 100 KWp Photovoltaic Park in Oraiokastro, Thessaloniki
  • Construction of Two Electrical Panels for 100 KWp PV Parks for parks in Corfu
  • Construction of Two Electrical Panels for 100 KWp PV Parks for parks in Macedonia
  • Design and Construction of Four Electrical Automation Panels for machinery to be exported to Romania

The company’s substations consist of :

  • Low-loss transformers from the Italian manufacturer Newton
  • Schneider Electric Medium Voltage Fields
  • Low Voltage Equipment from Schneider Electric

Additionally, the company proceeded with the sale of 3 low-loss Medium Voltage transformers from the Italian manufacturer Newton, with a total capacity of 2 MWp. The increased demand for these specific transformers is due to their significant performance advantage compared to standard market transformers, as well as their fast delivery times.